United States βΊ Grid βΊ Interconnection queues βΊ North Dakota
SOLAR + STORAGE Β· SPPSolar + storage project GEN-2023-160, Slope County
Solar + storage project GEN-2023-160, Slope County is a 300 MW solar + storage request withdrawn in the SPP interconnection queue, in Slope County, North Dakota, connecting to BEPC.
Queue statusWithdrawn / abandoned
- PlanningQueued Oct 2023 (completed)
- Withdrawn / abandonedMar 2024 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- GEN-2023-160
- Grid region
- SPP (Southwest Power Pool)
- Utility / transmission owner
- BEPC
- Connection point (POI)
- Belfield - Rhame 230 kV Line
- Location
- Slope County, North Dakota
- Technology
- Solar: 300 MW Β· Battery
- Total requested
- 300 MW
- Service type
- NRIS and ERIS
- Study phase
- WITHDRAWN
- Queue status
- Withdrawn
- Entered queue
- 2 October 2023
- Proposed online date
- December 2027
- Withdrawn
- March 2024
Location
Marker shows the centre of Slope County; the queue data does not give exact sites.
Power plants in North Dakota Β· Transmission lines in North Dakota
Other requests in Slope County
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem