United States β€Ί Grid β€Ί Interconnection queues β€Ί Michigan

ONSHORE WIND Β· MISO

Onshore wind project G418, Oceana County

Onshore wind project G418, Oceana County is a 140 MW onshore wind request withdrawn in the MISO interconnection queue, in Oceana County, Michigan.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Mar 2004 (completed)
  2. Withdrawn / abandonedDec 2010 (project stopped here)
  3. ConsentedDec 2010 (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
G418
Grid region
MISO (Midcontinent)
Connection point (POI)
Donaldson Creek 138 kV Substation
Location
Oceana County, Michigan
Technology
Wind: 140 MW
Total requested
140 MW
Study phase
Network Upgrade
Queue status
Withdrawn
Entered queue
22 March 2004
Agreement signed
7 December 2010
Proposed online date
May 2009
Withdrawn
December 2010

Location

Marker shows the centre of Oceana County; the queue data does not give exact sites.

Power plants in Michigan Β· Transmission lines in Michigan

Other requests in Oceana County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem