United States βΊ Grid βΊ Interconnection queues βΊ Michigan
ONSHORE WIND Β· MISOOnshore wind project H075, Oceana County
Onshore wind project H075, Oceana County is a 43.2 MW onshore wind request withdrawn in the MISO interconnection queue, in Oceana County, Michigan.
Queue statusWithdrawn / abandoned
- PlanningQueued Jun 2008 (completed)
- Withdrawn / abandoned (project stopped here)
- ConsentedOct 2010 (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- H075
- Grid region
- MISO (Midcontinent)
- Connection point (POI)
- METC Redwood Substation
- Location
- Oceana County, Michigan
- Technology
- Wind: 43.2 MW
- Total requested
- 43.2 MW
- Study phase
- Network Upgrade
- Queue status
- Withdrawn
- Entered queue
- 19 June 2008
- Agreement signed
- 4 October 2010
- Proposed online date
- December 2009
Location
Marker shows the centre of Oceana County; the queue data does not give exact sites.
Other requests in Oceana County
- Solar project J1071, Oceana CountySolar Β· 100 MW Β· under construction
- Battery storage project J2567, Oceana CountyBattery storage Β· 240 MW Β· in study
- Solar project J4048, Oceana CountySolar Β· 110 MW Β· in study
- Solar project J3065, Oceana CountySolar Β· 20.0 MW Β· in study
- Onshore wind project G418, Oceana CountyOnshore wind Β· 140 MW Β· withdrawn
- Onshore wind project G513, Oceana CountyOnshore wind Β· 100 MW Β· withdrawn
- Onshore wind project G228, Oceana CountyOnshore wind Β· 30.0 MW Β· withdrawn
- Onshore wind project G229, Oceana CountyOnshore wind Β· 30.0 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem