ONSHORE WIND Β· MISO

Onshore wind project H075, Oceana County

Onshore wind project H075, Oceana County is a 43.2 MW onshore wind request withdrawn in the MISO interconnection queue, in Oceana County, Michigan.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Jun 2008 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. ConsentedOct 2010 (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
H075
Grid region
MISO (Midcontinent)
Connection point (POI)
METC Redwood Substation
Location
Oceana County, Michigan
Technology
Wind: 43.2 MW
Total requested
43.2 MW
Study phase
Network Upgrade
Queue status
Withdrawn
Entered queue
19 June 2008
Agreement signed
4 October 2010
Proposed online date
December 2009

Location

Marker shows the centre of Oceana County; the queue data does not give exact sites.

Power plants in Michigan Β· Transmission lines in Michigan

Other requests in Oceana County