United States β€Ί Grid β€Ί Interconnection queues β€Ί Missouri

ONSHORE WIND Β· SPP

Onshore wind project GEN-2017-115, Atchison County

Onshore wind project GEN-2017-115, Atchison County is a 244 MW onshore wind request withdrawn in the SPP interconnection queue, in Atchison County, Missouri, connecting to KCPL.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Nov 2017 (completed)
  2. Withdrawn / abandonedNov 2025 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
GEN-2017-115
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
KCPL
Connection point (POI)
Holt County 345 kV
Location
Atchison County, Missouri
Technology
Wind: 244 MW
Total requested
244 MW
Service type
Energy only (ERIS)
Study phase
TERMINATED
Queue status
Withdrawn
Entered queue
10 November 2017
Proposed online date
December 2026
Withdrawn
November 2025

Location

Marker shows the centre of Atchison County; the queue data does not give exact sites.

Power plants in Missouri Β· Transmission lines in Missouri

Other requests in Atchison County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem