United States β€Ί Grid β€Ί Interconnection queues β€Ί Pennsylvania

SOLAR Β· PJM

Solar project AF1-024, Adams County

Solar project AF1-024, Adams County is a 19.9 MW solar request withdrawn in the PJM interconnection queue, in Adams County, Pennsylvania, connecting to PPL.

Queue statusWithdrawn / abandoned
  1. PlanningQueued May 2019 (completed)
  2. Withdrawn / abandonedMay 2019 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
AF1-024
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
PPL
Connection point (POI)
Freeland Municipal Authority
Location
Adams County, Pennsylvania
Technology
Solar: 19.9 MW
Total requested
19.9 MW
Service type
Network resource (NRIS)
Study phase
Feasibility Study
Queue status
Withdrawn
Entered queue
1 May 2019
Proposed online date
December 2021
Withdrawn
May 2019

Location

Marker shows the centre of Adams County; the queue data does not give exact sites.

Power plants in Pennsylvania Β· Transmission lines in Pennsylvania

Other requests in Adams County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem