United States › Grid › Interconnection queues › Nebraska
ONSHORE WIND · SPPOnshore wind project GEN-2002-023N, Hamilton County
Onshore wind project GEN-2002-023N, Hamilton County is a 0.8 MW onshore wind request built and operating in the SPP interconnection queue, in Hamilton County, Nebraska, connecting to NPPD.
Request details
- Queue ID
- GEN-2002-023N
- Grid region
- SPP (Southwest Power Pool)
- Utility / transmission owner
- NPPD
- Connection point (POI)
- Harmony 115kV
- Location
- Hamilton County, Nebraska
- Technology
- Wind: 0.8 MW
- Total requested
- 0.8 MW
- Service type
- Energy only (ERIS)
- Study phase
- IA FULLY EXECUTED/COMMERCIAL OPERATION
- Queue status
- Operational
- Entered queue
- 28 September 2002
Location
Marker shows the centre of Hamilton County; the queue data does not give exact sites.
Other requests in Hamilton County
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem