BATTERY STORAGE · NYISO

Arch Energy Storage

Arch Energy Storage is a 250 MW battery storage request withdrawn in the NYISO interconnection queue, in Orange County, New York, connecting to CHGE.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Jun 2023 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
1564
Grid region
NYISO (New York)
Utility / transmission owner
CHGE
Developer
Terra-Gen Development Company, LLC
Connection point (POI)
Rock Tavern 345kV Substation
Location
Orange County, New York
Technology
Battery: 250 MW
Total requested
250 MW
Queue status
Withdrawn
Entered queue
7 June 2023

Location

Marker shows the centre of Orange County; the queue data does not give exact sites.

Power plants in New York · Transmission lines in New York

Other requests in Orange County