🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Texas

OTHER · ERCOT

Pelton Lake Energy Storage

Pelton Lake Energy Storage is a 101 MW other request withdrawn in the ERCOT interconnection queue, in Brazoria County, Texas.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Nov 2023 (completed)
  2. Withdrawn / abandonedApr 2024 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
25INR0543
Grid region
ERCOT (Texas)
Developer
Pelton Lake Energy Storage, LLC
Connection point (POI)
Tap 138kV 44010 W_A_P_POI8A - 42980 NASH_S02_8 CKT #2
Location
Brazoria County, Texas
Technology
Other: 101 MW
Total requested
101 MW
Study phase
FIS
Queue status
Withdrawn
Entered queue
13 November 2023
Proposed online date
June 2026
Withdrawn
April 2024

Location

Marker shows the centre of Brazoria County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Brazoria County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem