United States βΊ Grid βΊ Interconnection queues βΊ New Jersey
GAS Β· PJMAtheina 480V
Atheina 480V is a 0.2 MW gas request withdrawn in the PJM interconnection queue, in Passaic County, New Jersey, connecting to PSEG.
Queue statusWithdrawn / abandoned
- PlanningQueued Apr 2017 (completed)
- Withdrawn / abandonedJun 2018 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- AD1-011
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- PSEG
- Connection point (POI)
- Athenia 480 v
- Location
- Passaic County, New Jersey
- Technology
- Gas: 0.2 MW
- Total requested
- 0.2 MW
- Service type
- Energy only (ERIS)
- Study phase
- Available studies: Feasibility Study, System Impact Study; Interim/Interconnection Service Agreement: Withdrawn
- Queue status
- Withdrawn
- Entered queue
- 3 April 2017
- Proposed online date
- January 2020
- Withdrawn
- June 2018
Location
Marker shows the centre of Passaic County; the queue data does not give exact sites.
Power plants in New Jersey Β· Transmission lines in New Jersey
Other requests in Passaic County
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem