United States › Grid › Interconnection queues › Iowa
ONSHORE WIND · MISOOnshore wind project G232, Dickinson County
Onshore wind project G232, Dickinson County is a 44.0 MW onshore wind request built and operating in the MISO interconnection queue, in Dickinson County, Iowa.
Request details
- Queue ID
- G232
- Grid region
- MISO (Midcontinent)
- Connection point (POI)
- Unknown
- Location
- Dickinson County, Iowa
- Technology
- Wind: 44.0 MW
- Total requested
- 44.0 MW
- Study phase
- SPA - SIS
- Queue status
- Operational
- Entered queue
- 29 May 2002
- Agreement signed
- 31 March 2003
- Proposed online date
- January 2007
- Came online
- January 2007
Location
Marker shows the centre of Dickinson County; the queue data does not give exact sites.
Other requests in Dickinson County
- Onshore wind project J982, Dickinson CountyOnshore wind · 300 MW · agreement signed
- Onshore wind project G298, Dickinson CountyOnshore wind · 100 MW · built
- Onshore wind project G538, Dickinson CountyOnshore wind · 50.0 MW · built
- Onshore wind project J2040, Dickinson CountyOnshore wind · 150 MW · withdrawn
- Onshore wind project J068, Dickinson CountyOnshore wind · 100 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem