United States βΊ Grid βΊ Interconnection queues βΊ Maryland
SOLAR Β· PJMSolar project W2-002, Kent County
Solar project W2-002, Kent County is a 20.0 MW solar request withdrawn in the PJM interconnection queue, in Kent County, Maryland, connecting to DPL.
Queue statusWithdrawn / abandoned
- PlanningQueued May 2010 (completed)
- Withdrawn / abandonedDec 2010 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- W2-002
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- DPL
- Connection point (POI)
- Kennedyville 1 69kV
- Location
- Kent County, Maryland
- Technology
- Solar: 20.0 MW
- Total requested
- 20.0 MW
- Service type
- Network resource (NRIS)
- Study phase
- Available studies: Feasibility Study
- Queue status
- Withdrawn
- Entered queue
- 10 May 2010
- Proposed online date
- December 2011
- Withdrawn
- December 2010
Location
Marker shows the centre of Kent County; the queue data does not give exact sites.
Other requests in Kent County
- Morgnec Road SolarSolar Β· 55.8 MW Β· agreement signed
- Mills Branch Wind FarmOnshore wind Β· 100 MW Β· withdrawn
- Solar project AB2-143, Kent CountySolar Β· 20.0 MW Β· withdrawn
- Solar project W2-003, Kent CountySolar Β· 20.0 MW Β· withdrawn
- Solar project AB2-183, Kent CountySolar Β· 20.0 MW Β· withdrawn
- Solar project X3-074, Kent CountySolar Β· 11.9 MW Β· withdrawn
- Solar project Z2-096, Kent CountySolar Β· 10.0 MW Β· withdrawn
- Solar project X3-073, Kent CountySolar Β· 9.8 MW Β· withdrawn
- Solar project Z2-074, Kent CountySolar Β· 6.0 MW Β· withdrawn
- Blue Star Solar ProjectSolar Β· 6.0 MW Β· withdrawn
- Solar project Z2-075, Kent CountySolar Β· 5.5 MW Β· withdrawn
- Solar project Z2-073, Kent CountySolar Β· 5.0 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem