Solar + storage project SGI-PNM-2010-16, Bernalillo County

Solar + storage project SGI-PNM-2010-16, Bernalillo County is a 0.5 MW solar + storage request built and operating in the West interconnection queue, in Bernalillo County, New Mexico, connecting to Public Service Company of New Mexico.

Queue statusOperating
  1. PlanningQueued Sep 2010 (completed)
  2. ConsentedMar 2011 (completed)
  3. Construction (completed)
  4. Operating (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
SGI-PNM-2010-16
Grid region
West (non-ISO utilities)
Utility / transmission owner
Public Service Company of New Mexico
Connection point (POI)
PNM-RGD Studio Feeder 14
Location
Bernalillo County, New Mexico
Technology
Solar: 0.5 MW · Battery
Total requested
0.5 MW
Service type
Network resource (NRIS)
Study phase
SGIA executed 3/3/2011.
Queue status
Operational
Entered queue
2 September 2010
Agreement signed
3 March 2011

Location

Marker shows the centre of Bernalillo County; the queue data does not give exact sites.

Power plants in New Mexico · Transmission lines in New Mexico

Other requests in Bernalillo County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem