πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Oklahoma

ONSHORE WIND Β· SPP

Onshore wind project GEN-2016-042, Grady County

Onshore wind project GEN-2016-042, Grady County is a 22.0 MW onshore wind request withdrawn in the SPP interconnection queue, in Grady County, Oklahoma, connecting to AEP.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Mar 2016 (completed)
  2. Withdrawn / abandonedMar 2017 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. OperatingDec 2016 (not reached)
  6. Closed (not reached)

Request details

Queue ID
GEN-2016-042
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
AEP
Connection point (POI)
Tap Lawton - Sunnyside 345kV
Location
Grady County, Oklahoma
Technology
Wind: 22.0 MW
Total requested
22.0 MW
Service type
Energy only (ERIS)
Study phase
WITHDRAWN
Queue status
Withdrawn
Entered queue
30 March 2016
Proposed online date
December 2016
Came online
December 2016
Withdrawn
March 2017

Location

Marker shows the centre of Grady County; the queue data does not give exact sites.

Power plants in Oklahoma Β· Transmission lines in Oklahoma

Other requests in Grady County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem