United States βΊ Grid βΊ Interconnection queues βΊ Ohio
SOLAR Β· PJMSolar project AC2-043, Fairfield County
Solar project AC2-043, Fairfield County is a 50.0 MW solar request withdrawn in the PJM interconnection queue, in Fairfield County, Ohio, connecting to AEP.
Queue statusWithdrawn / abandoned
- PlanningQueued Feb 2017 (completed)
- Withdrawn / abandonedSep 2018 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- AC2-043
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- AEP
- Connection point (POI)
- W. Millersport-S. Baltimore 138kV
- Location
- Fairfield County, Ohio
- Technology
- Solar: 50.0 MW
- Total requested
- 50.0 MW
- Service type
- Network resource (NRIS)
- Study phase
- Available studies: Feasibility Study, System Impact Study
- Queue status
- Withdrawn
- Entered queue
- 6 February 2017
- Proposed online date
- December 2018
- Withdrawn
- September 2018
Location
Marker shows the centre of Fairfield County; the queue data does not give exact sites.
Other requests in Fairfield County
- Eastern Cottontail SolarSolar Β· 220 MW Β· agreement signed
- Appalachian Cottontail SolarSolar Β· 114 MW Β· agreement signed
- CarnationSolar Β· 84.0 MW Β· agreement signed
- CarnationSolar Β· 58.0 MW Β· agreement signed
- Ripley Solar IISolar Β· 100 MW Β· withdrawn
- Solar project AG2-003, Fairfield CountySolar Β· 20.0 MW Β· withdrawn
- Solar project AH1-032, Fairfield CountySolar Β· 18.0 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem