United States › Grid › Interconnection queues › Texas

GAS · ERCOT

Brotman U1 U2 Power Station

Brotman U1 U2 Power Station is a 102 MW gas request built and operating in the ERCOT interconnection queue, in Brazoria County, Texas.

Queue statusOperating
  1. PlanningQueued Mar 2023 (completed)
  2. Consented (completed)
  3. Construction (completed)
  4. OperatingJun 2023 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
23INR0613
Grid region
ERCOT (Texas)
Location
Brazoria County, Texas
Technology
Gas: 102 MW
Total requested
102 MW
Study phase
IA Executed
Queue status
Operational
Entered queue
26 March 2023
Came online
June 2023

Location

Marker shows the centre of Brazoria County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Brazoria County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem