πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Georgia

GAS Β· SOUTHEAST

Gas project IC-240, Coweta County

Gas project IC-240, Coweta County is a 952 MW gas request withdrawn in the Southeast interconnection queue, in Coweta County, Georgia, connecting to Southern Company.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Aug 2010 (completed)
  2. Withdrawn / abandonedJul 2011 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
IC-240
Grid region
Southeast (non-ISO utilities)
Utility / transmission owner
Southern Company
Connection point (POI)
Yates 230 kV Substation
Location
Coweta County, Georgia
Technology
Gas: 952 MW
Total requested
952 MW
Service type
Energy only (ERIS)
Study phase
Withdrawn
Queue status
Withdrawn
Entered queue
9 August 2010
Withdrawn
July 2011

Location

Marker shows the centre of Coweta County; the queue data does not give exact sites.

Power plants in Georgia Β· Transmission lines in Georgia

Other requests in Coweta County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem