United States › Grid › Interconnection queues › Georgia
SOLAR · SOUTHEASTSR Snipesville III
SR Snipesville III is a 103 MW solar request built and operating in the Southeast interconnection queue, in Jeff Davis County, Georgia, connecting to Georgia Transmission.
Request details
- Queue ID
- GI-140
- Grid region
- Southeast (non-ISO utilities)
- Utility / transmission owner
- Georgia Transmission
- Connection point (POI)
- Denton Still Road 230 kV Sub
- Location
- Jeff Davis County, Georgia
- Technology
- Solar: 103 MW
- Total requested
- 103 MW
- Study phase
- IA Executed
- Queue status
- Operational
- Entered queue
- 31 December 2023
- Came online
- March 2023
Location
Marker shows the centre of Jeff Davis County; the queue data does not give exact sites.
Other requests in Jeff Davis County
- Solar project IC-1014, Jeff Davis CountySolar · 230 MW · suspended
- SR Snipesville IISolar · 118 MW · built
- SR Snipesville ISolar · 90.0 MW · built
- SR Hazlehurst II (aka S. Loving)Solar · 53.0 MW · built
- SR Hazlehurst IIISolar · 44.0 MW · built
- Solar project IC-537, Jeff Davis CountySolar · 215 MW · withdrawn
- Solar project IC-726, Jeff Davis CountySolar · 215 MW · withdrawn
- Solar project IC-349, Jeff Davis CountySolar · 215 MW · withdrawn
- Solar project IC-299, Jeff Davis CountySolar · 10.0 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem