🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Georgia

OTHER · SOUTHEAST

Piedmont Green Power

Piedmont Green Power is a 53.0 MW other request built and operating in the Southeast interconnection queue, in Lamar County, Georgia, connecting to Southern Company.

Queue statusOperating
  1. Planning (completed)
  2. ConsentedMar 2010 (completed)
  3. Construction (completed)
  4. OperatingApr 2013 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
IC-229
Grid region
Southeast (non-ISO utilities)
Utility / transmission owner
Southern Company
Location
Lamar County, Georgia
Technology
Other: 53.0 MW
Total requested
53.0 MW
Study phase
Operational
Queue status
Operational
Agreement signed
31 March 2010
Came online
April 2013

Location

Marker shows the centre of Lamar County; the queue data does not give exact sites.

Power plants in Georgia · Transmission lines in Georgia

Other requests in Lamar County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem