United States βΊ Grid βΊ Interconnection queues βΊ Nebraska
SOLAR Β· SPPSolar project GEN-2022-057
Solar project GEN-2022-057 is a 87.0 MW solar request withdrawn in the SPP interconnection queue, connecting to Tri-State.
Queue statusWithdrawn / abandoned
- PlanningQueued Jun 2022 (completed)
- Withdrawn / abandonedNov 2023 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- OperatingDec 2025 (not reached)
- Closed (not reached)
Request details
- Queue ID
- GEN-2022-057
- Grid region
- SPP (Southwest Power Pool)
- Utility / transmission owner
- Tri-State
- Connection point (POI)
- Elsie Tap 115 kV
- Location
- Nebraska
- Technology
- Solar: 87.0 MW
- Total requested
- 87.0 MW
- Service type
- NRIS and ERIS
- Study phase
- WITHDRAWN
- Queue status
- Withdrawn
- Entered queue
- 23 June 2022
- Proposed online date
- December 2025
- Came online
- December 2025
- Withdrawn
- November 2023
Location
No county location in the queue data.
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem