Solar project GEN-2022-057

Solar project GEN-2022-057 is a 87.0 MW solar request withdrawn in the SPP interconnection queue, connecting to Tri-State.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Jun 2022 (completed)
  2. Withdrawn / abandonedNov 2023 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. OperatingDec 2025 (not reached)
  6. Closed (not reached)

Request details

Queue ID
GEN-2022-057
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
Tri-State
Connection point (POI)
Elsie Tap 115 kV
Location
Nebraska
Technology
Solar: 87.0 MW
Total requested
87.0 MW
Service type
NRIS and ERIS
Study phase
WITHDRAWN
Queue status
Withdrawn
Entered queue
23 June 2022
Proposed online date
December 2025
Came online
December 2025
Withdrawn
November 2023

Location

No county location in the queue data.