Kendall Energy Center

Kendall Energy Center is a 20.0 MW gas request built and operating in the PJM interconnection queue, in Grundy County, Illinois, connecting to ComEd.

Queue statusOperating
  1. PlanningQueued Apr 2013 (completed)
  2. Consented (completed)
  3. Construction (completed)
  4. OperatingMay 2017 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
Y3-090
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
ComEd
Connection point (POI)
Kendall III
Location
Grundy County, Illinois
Technology
Gas: 20.0 MW
Total requested
20.0 MW
Service type
Network resource (NRIS)
Study phase
Available studies: Feasibility Study, System Impact Study, Facilities Study; Interim/Interconnection Service Agreement:
Queue status
Operational
Entered queue
26 April 2013
Proposed online date
December 2015
Came online
May 2017

Location

Marker shows the centre of Grundy County; the queue data does not give exact sites.

Power plants in Illinois · Transmission lines in Illinois

Other requests in Grundy County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem