United States βΊ Grid βΊ Interconnection queues βΊ Tennessee
SOLAR Β· SOUTHEASTSolar project 633, Grundy County
Solar project 633, Grundy County is a 150 MW solar request withdrawn in the Southeast interconnection queue, in Grundy County, Tennessee, connecting to Tennessee Valley Authority.
Queue statusWithdrawn / abandoned
- PlanningQueued Jul 2024 (completed)
- Withdrawn / abandoned (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- 633
- Grid region
- Southeast (non-ISO utilities)
- Utility / transmission owner
- Tennessee Valley Authority
- Location
- Grundy County, Tennessee
- Technology
- Solar: 150 MW
- Total requested
- 150 MW
- Queue status
- Withdrawn
- Entered queue
- 1 July 2024
Location
Marker shows the centre of Grundy County; the queue data does not give exact sites.
Power plants in Tennessee Β· Transmission lines in Tennessee
Other requests in Grundy County
- Solar project 507, Grundy CountySolar Β· 160 MW Β· withdrawn
- Onshore wind project 227, Grundy CountyOnshore wind Β· 151 MW Β· withdrawn
- Solar project 460, Grundy CountySolar Β· 150 MW Β· withdrawn
- Gas project 224, Grundy CountyGas Β· 130 MW Β· withdrawn
- Solar + storage project 555, Grundy CountySolar + storage Β· 40.0 MW Β· withdrawn
- Battery storage project 554, Grundy CountyBattery storage Β· -75.0 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem