Sharon Springs Interconnection

Sharon Springs Interconnection is a 20.0 MW solar request withdrawn in the NYISO interconnection queue, in Schoharie County, New York, connecting to NM-NG.

Queue statusWithdrawn / abandoned
  1. PlanningQueued May 2019 (completed)
  2. Withdrawn / abandonedJul 2021 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
841
Grid region
NYISO (New York)
Utility / transmission owner
NM-NG
Developer
TJA Clean Energy, LLC
Connection point (POI)
Sharon - Cobleskill 69kV Substation
Location
Schoharie County, New York
Technology
Solar: 20.0 MW
Total requested
20.0 MW
Queue status
Withdrawn
Entered queue
10 May 2019
Withdrawn
July 2021

Location

Marker shows the centre of Schoharie County; the queue data does not give exact sites.