United States βΊ Grid βΊ Interconnection queues βΊ New York
BATTERY STORAGE Β· NYISOBlenheim Gilboa Storage
Blenheim Gilboa Storage is a 120 MW battery storage request built and operating in the NYISO interconnection queue, connecting to NYPA.
Request details
- Queue ID
- 185
- Grid region
- NYISO (New York)
- Utility / transmission owner
- NYPA
- Developer
- NY Power Authority
- Connection point (POI)
- Valenti Rd., Gilboa 345kV
- Location
- New York
- Technology
- Other Storage: 120 MW
- Total requested
- 120 MW
- Study phase
- SRIS, CY06
- Queue status
- Operational
- Entered queue
- 29 March 2005
Location
Marker shows the centre of County; the queue data does not give exact sites.
Other requests in County
- Wheelhouse Energy StorageBattery storage Β· 200 MW Β· in study
- Rock District SolarSolar Β· 20.0 MW Β· in study
- Blenheim Gilboa StorageBattery storage Β· 120 MW Β· built
- East Point SolarSolar Β· 50.0 MW Β· built
- East Point SolarSolar Β· 50.0 MW Β· built
- Schoharie HighlandsOnshore wind Β· 70.0 MW Β· withdrawn
- Line Creek SolarSolar Β· 50.0 MW Β· withdrawn
- Line Creek ESBattery storage Β· 30.0 MW Β· withdrawn
- Sharon SolarSolar Β· 20.0 MW Β· withdrawn
- Warner Hill SolarSolar Β· 20.0 MW Β· withdrawn
- Cobleskill SolarSolar Β· 20.0 MW Β· withdrawn
- ELP Middleburgh SolarSolar Β· 20.0 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem