LEVEE (Freeport LNG)

LEVEE (Freeport LNG) is a 11.0 MW gas request built and operating in the ERCOT interconnection queue, in Brazoria County, Texas.

Queue statusOperating
  1. PlanningQueued Dec 2011 (completed)
  2. ConsentedJan 2014 (completed)
  3. Construction (completed)
  4. OperatingDec 2019 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
16INR0003
Grid region
ERCOT (Texas)
Developer
Freeport LNG
Connection point (POI)
43336 Oyster Cr 138kV
Location
Brazoria County, Texas
Technology
Gas: 11.0 MW
Total requested
11.0 MW
Study phase
IA
Queue status
Operational
Entered queue
14 December 2011
Agreement signed
13 January 2014
Proposed online date
December 2019
Came online
December 2019

Location

Marker shows the centre of Brazoria County; the queue data does not give exact sites.