All Star Solar

All Star Solar is a 95.0 MW solar request in interconnection study in the Southeast interconnection queue, in Appling County, Georgia, connecting to Georgia Transmission.

Queue statusIn planning
  1. PlanningQueued Oct 2019 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingOct 2023 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
GI-124
Grid region
Southeast (non-ISO utilities)
Utility / transmission owner
Georgia Transmission
Connection point (POI)
Pine Grove 115 kV Substation
Location
Appling County, Georgia
Technology
Solar: 95.0 MW
Total requested
95.0 MW
Study phase
Facilities Study
Queue status
Active
Entered queue
4 October 2019
Proposed online date
December 2023
Came online
October 2023

Location

Marker shows the centre of Appling County; the queue data does not give exact sites.

Power plants in Georgia · Transmission lines in Georgia

Other requests in Appling County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem