Moss Ridge Solar is a 60.0 MW solar request withdrawn in the NYISO interconnection queue, in St. Lawrence County, New York, connecting to NM-NG.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Mar 2021 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
1150
Grid region
NYISO (New York)
Utility / transmission owner
NM-NG
Developer
Moss Ridge Solar 1, LLC
Connection point (POI)
Corning - Battle Hill 115 kV line #4
Location
St. Lawrence County, New York
Technology
Solar: 60.0 MW
Total requested
60.0 MW
Queue status
Withdrawn
Entered queue
16 March 2021

Location

Marker shows the centre of St. Lawrence County; the queue data does not give exact sites.

Power plants in New York Β· Transmission lines in New York

Other requests in St. Lawrence County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem