United States › Grid › Interconnection queues › New York
BATTERY STORAGE · NYISORiverbank Power D1
Riverbank Power D1 is a 1,000 MW battery storage request withdrawn in the NYISO interconnection queue, in St. Lawrence County, New York, connecting to NYPA.
Queue statusWithdrawn / abandoned
- PlanningQueued Feb 2008 (completed)
- Withdrawn / abandonedMar 2010 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- 279
- Grid region
- NYISO (New York)
- Utility / transmission owner
- NYPA
- Developer
- Riverbank Power Corporation
- Connection point (POI)
- Massena 765kV
- Location
- St. Lawrence County, New York
- Technology
- Other Storage: 1,000 MW
- Total requested
- 1,000 MW
- Queue status
- Withdrawn
- Entered queue
- 20 February 2008
- Withdrawn
- March 2010
Location
Marker shows the centre of St. Lawrence County; the queue data does not give exact sites.
Other requests in St. Lawrence County
- Rich Road Solar Energy CenterSolar + storage · 240 MW · in study
- NY125B - Two Rivers SolarSolar · 200 MW · in study
- Gateway Solar Energy CenterSolar · 180 MW · in study
- Morris SolarSolar · 20.0 MW · in study
- Fairway SolarSolar · 20.0 MW · in study
- BR Benson Mines SolarSolar · 12.1 MW · in study
- Riverbank Power D2Hydro · 1,000 MW · withdrawn
- Cedar Lake StorageBattery storage · 300 MW · withdrawn
- Rich Road Solar Energy CenterSolar + storage · 240 MW · withdrawn
- Amber Solar and StorageSolar + storage · 232 MW · withdrawn
- St Lawrence Data and Agricultural CenterOther · 200 MW · withdrawn
- NY125B - Two Rivers SolarSolar · 200 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem