Solar project 1078, Lincoln County

Solar project 1078, Lincoln County is a 80.0 MW solar request withdrawn in the West interconnection queue, in Lincoln County, Wyoming, connecting to PacifiCorp.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Oct 2018 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
1078
Grid region
West (non-ISO utilities)
Utility / transmission owner
PacifiCorp
Connection point (POI)
Naughton Treasureton transmission line
Location
Lincoln County, Wyoming
Technology
Solar: 80.0 MW
Total requested
80.0 MW
Service type
Network resource (NRIS)
Study phase
Request moved to transition cluster
Queue status
Withdrawn
Entered queue
23 October 2018
Proposed online date
December 2021

Location

Marker shows the centre of Lincoln County; the queue data does not give exact sites.

Power plants in Wyoming Β· Transmission lines in Wyoming

Other requests in Lincoln County