ONSHORE WIND Β· SPP

Onshore wind project GEN-2004-006, Geary County

Onshore wind project GEN-2004-006, Geary County is a 100 MW onshore wind request withdrawn in the SPP interconnection queue, in Geary County, Kansas, connecting to WERE.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Mar 2004 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
GEN-2004-006
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
WERE
Location
Geary County, Kansas
Technology
Wind: 100 MW
Total requested
100 MW
Service type
Energy only (ERIS)
Study phase
WITHDRAWN
Queue status
Withdrawn
Entered queue
25 March 2004
Proposed online date
December 2005

Location

Marker shows the centre of Geary County; the queue data does not give exact sites.

Power plants in Kansas Β· Transmission lines in Kansas

Other requests in Geary County