BATTERY STORAGE · ERCOTYorktown BESS
Yorktown BESS is a 151 MW battery storage request in interconnection study in the ERCOT interconnection queue, in Dewitt County, Texas.
Queue statusIn planning
- PlanningQueued Oct 2023 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Dec 2026 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- 26INR0328
- Grid region
- ERCOT (Texas)
- Developer
- Navitas Energy LLC
- Connection point (POI)
- (#78575) LCRA Yorktown 138 kV
- Location
- Dewitt County, Texas
- Technology
- Battery: 151 MW
- Total requested
- 151 MW
- Study phase
- SS Completed, FIS Started, No IA
- Queue status
- Active
- Entered queue
- 25 October 2023
- Proposed online date
- December 2026
Location
Marker shows the centre of Dewitt County; the queue data does not give exact sites.
Other requests in Dewitt County
- Shaula II SolarSolar + storage · 205 MW · agreement signed
- Shaula I SolarSolar + storage · 205 MW · agreement signed
- Shaula I BESSSolar + storage · 206 MW · in study
- Shaula III SolarSolar + storage · 205 MW · in study
- Bayside II SolarSolar · 253 MW · suspended
- Bayside 2 BESSBattery storage · 252 MW · suspended
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem