Liberty Gap WF is a 155 MW onshore wind request withdrawn in the PJM interconnection queue, in Pendleton County, West Virginia, connecting to APS.
Queue statusWithdrawn / abandoned
- PlanningQueued Nov 2002 (completed)
- Withdrawn / abandonedJun 2010 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- J07
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- APS
- Connection point (POI)
- North Franklin 138kV
- Location
- Pendleton County, West Virginia
- Technology
- Wind: 155 MW
- Total requested
- 155 MW
- Service type
- Energy only (ERIS)
- Study phase
- Available studies: Feasibility Study, System Impact Study, Facilities Study; Interim/Interconnection Service Agreement:
- Queue status
- Withdrawn
- Entered queue
- 1 November 2002
- Proposed online date
- November 2011
- Withdrawn
- June 2010
Location
Marker shows the centre of Pendleton County; the queue data does not give exact sites.
Power plants in West Virginia · Transmission lines in West Virginia
Other requests in Pendleton County
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem