United States βΊ Grid βΊ Interconnection queues βΊ Texas
GAS Β· ERCOTDaltus DG
Daltus DG is a 19.5 MW gas request withdrawn in the ERCOT interconnection queue, in Reeves County, Texas.
Queue statusWithdrawn / abandoned
- PlanningQueued Mar 2021 (completed)
- Withdrawn / abandonedFeb 2022 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- 22INR0461
- Grid region
- ERCOT (Texas)
- Developer
- Duke Energy One, Inc.
- Connection point (POI)
- 60721 Cryo4A 138kV
- Location
- Reeves County, Texas
- Technology
- Gas: 19.5 MW
- Total requested
- 19.5 MW
- Study phase
- FIS
- Queue status
- Withdrawn
- Entered queue
- 15 March 2021
- Proposed online date
- January 2024
- Withdrawn
- February 2022
Location
Marker shows the centre of Reeves County; the queue data does not give exact sites.
Other requests in Reeves County
- Cantaloupe SolarSolar Β· 307 MW Β· agreement signed
- August Draw SolarSolar Β· 250 MW Β· agreement signed
- Bracero Pecan StorageBattery storage Β· 238 MW Β· agreement signed
- Tolivar Power Plant (TEF- Due Diligence)Gas Β· 225 MW Β· agreement signed
- Elm Street BESS2Battery storage Β· 10.0 MW Β· agreement signed
- Saddleback AGR1Other Β· 10.0 MW Β· agreement signed
- Coyote Springs AGR1Other Β· 10.0 MW Β· agreement signed
- County Road BESSBattery storage Β· 9.9 MW Β· agreement signed
- Elm Street BESSBattery storage Β· 9.9 MW Β· agreement signed
- Wolf Bone North Energy CenterGas Β· 1,204 MW Β· in study
- Kilby1 Part 4 Large Block Simple CycleGas Β· 950 MW Β· in study
- Exergy Energy West Texas Natural Gas Reciprocating Power IGas Β· 400 MW Β· in study
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem