United States βΊ Grid βΊ Interconnection queues βΊ New York
GAS Β· NYISOCaithness Long Island II
Caithness Long Island II is a 632 MW gas request withdrawn in the NYISO interconnection queue, in Suffolk County, New York, connecting to LIPA.
Queue statusWithdrawn / abandoned
- PlanningQueued Mar 2013 (completed)
- Withdrawn / abandonedSep 2018 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- 401
- Grid region
- NYISO (New York)
- Utility / transmission owner
- LIPA
- Developer
- Caithness Long Island II, LLC
- Connection point (POI)
- Sills Road Substation 138kV
- Location
- Suffolk County, New York
- Technology
- Gas: 632 MW Β· Oil
- Total requested
- 632 MW
- Queue status
- Withdrawn
- Entered queue
- 22 March 2013
- Withdrawn
- September 2018
Location
Marker shows the centre of Suffolk County; the queue data does not give exact sites.
Other requests in Suffolk County
- Sunrise WindOffshore wind Β· 880 MW Β· in study
- East Setauket Storage IIBattery storage Β· 248 MW Β· in study
- Kce NY 37Battery storage Β· 150 MW Β· in study
- Ramadi Utility StorageBattery storage Β· 140 MW Β· in study
- Marathon BESSBattery storage Β· 135 MW Β· in study
- East Setauket Energy StorageBattery storage Β· 125 MW Β· in study
- Holtsville 138kV Energy StorageBattery storage Β· 110 MW Β· in study
- Horseblock Energy StorageBattery storage Β· 100 MW Β· in study
- Holtsville Brookhaven Battery StorageBattery storage Β· 79.9 MW Β· in study
- Kce NY 29Battery storage Β· 79.0 MW Β· in study
- Daphne Energy StorageBattery storage Β· 75.0 MW Β· in study
- Clies 70MWBattery storage Β· 70.0 MW Β· in study
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem