πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Virginia

SOLAR Β· PJM

Solar project AH1-324, Surry County

Solar project AH1-324, Surry County is a 80.0 MW solar request withdrawn in the PJM interconnection queue, in Surry County, Virginia, connecting to Dominion.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Mar 2025 (completed)
  2. Withdrawn / abandonedDec 2025 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
AH1-324
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
Dominion
Developer
Invenergy Solar Project Development LLC
Connection point (POI)
Colonial Trail - Surry 230 kV
Location
Surry County, Virginia
Technology
Solar: 80.0 MW
Total requested
80.0 MW
Service type
Network resource (NRIS)
Study phase
System Impact Study
Queue status
Withdrawn
Entered queue
28 March 2025
Proposed online date
December 2025
Withdrawn
December 2025

Location

Marker shows the centre of Surry County; the queue data does not give exact sites.

Power plants in Virginia Β· Transmission lines in Virginia

Other requests in Surry County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem