BATTERY STORAGE · NYISO

Columbia Storage

Columbia Storage is a 20.0 MW battery storage request withdrawn in the NYISO interconnection queue, in Herkimer County, New York, connecting to NYPA.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Mar 2022 (completed)
  2. Withdrawn / abandonedDec 2022 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
1359
Grid region
NYISO (New York)
Utility / transmission owner
NYPA
Developer
EDF Renewable Development, Inc
Connection point (POI)
Edic - Fraser 345 kV
Location
Herkimer County, New York
Technology
Battery: 20.0 MW
Total requested
20.0 MW
Queue status
Withdrawn
Entered queue
31 March 2022
Withdrawn
December 2022

Location

Marker shows the centre of Herkimer County; the queue data does not give exact sites.

Power plants in New York · Transmission lines in New York

Other requests in Herkimer County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem