Stewart Rock Energy Storage

Stewart Rock Energy Storage is a 150 MW battery storage request withdrawn in the NYISO interconnection queue, in Orange County, New York, connecting to CHG&E.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Oct 2022 (completed)
  2. Withdrawn / abandonedDec 2023 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
1450
Grid region
NYISO (New York)
Utility / transmission owner
CHG&E
Developer
NYG Energy LLC
Connection point (POI)
Rock Tavern 345KV
Location
Orange County, New York
Technology
Battery: 150 MW
Total requested
150 MW
Queue status
Withdrawn
Entered queue
11 October 2022
Withdrawn
December 2023

Location

Marker shows the centre of Orange County; the queue data does not give exact sites.