Pinewood Solar

Pinewood Solar is a 151 MW solar request with a signed interconnection agreement in the ERCOT interconnection queue, in Brazoria County, Texas.

Queue statusConsented
  1. PlanningQueued Sep 2022 (completed)
  2. ConsentedMay 2025 (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Oct 2027 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
25INR0170
Grid region
ERCOT (Texas)
Developer
Brazoria Solar II, LLC
Connection point (POI)
43020 Seabreeze 345kV
Location
Brazoria County, Texas
Technology
Solar: 151 MW
Total requested
151 MW
Study phase
SS Completed, FIS Completed, IA
Queue status
Active
Entered queue
2 September 2022
Agreement signed
8 May 2025
Proposed online date
October 2027

Location

Marker shows the centre of Brazoria County; the queue data does not give exact sites.