United States › Grid › Interconnection queues › Pennsylvania
ONSHORE WIND · NYISOBlack Cherry Wind 2
Black Cherry Wind 2 is a 300 MW onshore wind request withdrawn in the NYISO interconnection queue, in Mckean County, Pennsylvania, connecting to NM-NG.
Queue statusWithdrawn / abandoned
- PlanningQueued Dec 2023 (completed)
- Withdrawn / abandoned (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- 1648
- Grid region
- NYISO (New York)
- Utility / transmission owner
- NM-NG
- Developer
- Black Cherry Wind Power
- Connection point (POI)
- Five Mile - Homer City 345 kV line
- Location
- Mckean County, Pennsylvania
- Technology
- Wind: 300 MW
- Total requested
- 300 MW
- Queue status
- Withdrawn
- Entered queue
- 5 December 2023
Location
Marker shows the centre of Mckean County; the queue data does not give exact sites.
Power plants in Pennsylvania · Transmission lines in Pennsylvania
Other requests in Mckean County
- Ridgeway SolarSolar · 120 MW · agreement signed
- Bradford SolarSolar · 101 MW · agreement signed
- Stargazer IISolar + storage · 325 MW · in study
- Stargazer ISolar + storage · 325 MW · in study
- Solar project AI2-063, Mckean CountySolar · 82.5 MW · in study
- Black Cherry BESSBattery storage · 400 MW · withdrawn
- Black Cherry BatteryBattery storage · 400 MW · withdrawn
- McKean County Solar CSR Phase 2Solar + storage · 325 MW · withdrawn
- McKean County Solar CSR Phase 1Solar + storage · 325 MW · withdrawn
- Black Cherry Wind 1Onshore wind · 300 MW · withdrawn
- McKean County Solar IISolar · 240 MW · withdrawn
- Lewis Run - Pierce Brook 230 kVSolar · 240 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem