Onshore wind project GEN-2016-129, Pushmataha County

Onshore wind project GEN-2016-129, Pushmataha County is a 132 MW onshore wind request withdrawn in the SPP interconnection queue, in Pushmataha County, Oklahoma, connecting to AEP.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Nov 2016 (completed)
  2. Withdrawn / abandonedMar 2020 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
GEN-2016-129
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
AEP
Connection point (POI)
Valliant 345 kV substation
Location
Pushmataha County, Oklahoma
Technology
Wind: 132 MW
Total requested
132 MW
Service type
Energy only (ERIS)
Study phase
WITHDRAWN
Queue status
Withdrawn
Entered queue
30 November 2016
Proposed online date
December 2019
Withdrawn
March 2020

Location

Marker shows the centre of Pushmataha County; the queue data does not give exact sites.