Onshore wind project G0211, Douglas County

Onshore wind project G0211, Douglas County is a 127 MW onshore wind request withdrawn in the West interconnection queue, in Douglas County, Washington.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Nov 2005 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
G0211
Grid region
West (non-ISO utilities)
Connection point (POI)
to be determined
Location
Douglas County, Washington
Technology
Wind: 127 MW
Total requested
127 MW
Service type
Network resource (NRIS)
Queue status
Withdrawn
Entered queue
14 November 2005
Proposed online date
October 2007

Location

Marker shows the centre of Douglas County; the queue data does not give exact sites.

Power plants in Washington Β· Transmission lines in Washington

Other requests in Douglas County