πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Utah

GAS Β· WEST

Gas project 15, Juab County

Gas project 15, Juab County is a 550 MW gas request withdrawn in the West interconnection queue, in Juab County, Utah, connecting to PacifiCorp.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Oct 2001 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. ConsentedDec 2004 (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
15
Grid region
West (non-ISO utilities)
Utility / transmission owner
PacifiCorp
Developer
Spring Canyon Energy, LLC
Connection point (POI)
Mona substation
Location
Juab County, Utah
Technology
Gas: 550 MW
Total requested
550 MW
Service type
Network resource (NRIS)
Study phase
IA signed 12/13/04, REMOVED-LACK OF PROGRESS
Queue status
Withdrawn
Entered queue
11 October 2001
Agreement signed
13 December 2004
Proposed online date
June 2005

Location

Marker shows the centre of Juab County; the queue data does not give exact sites.

Power plants in Utah Β· Transmission lines in Utah

Other requests in Juab County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem