United States βΊ Grid βΊ Interconnection queues βΊ Kentucky
SOLAR Β· MISOSolar project J753, Breckinridge County
Solar project J753, Breckinridge County is a 100 MW solar request withdrawn in the MISO interconnection queue, in Breckinridge County, Kentucky, connecting to BIG RIVERS ELECTRIC CORPORATION.
Queue statusWithdrawn / abandoned
- PlanningQueued Nov 2016 (completed)
- Withdrawn / abandonedOct 2025 (project stopped here)
- ConsentedMar 2019 (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- J753
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- BIG RIVERS ELECTRIC CORPORATION
- Connection point (POI)
- Hardinsburg Sub 161kV
- Location
- Breckinridge County, Kentucky
- Technology
- Solar: 100 MW
- Total requested
- 100 MW
- Service type
- Network resource (NRIS)
- Study phase
- Study Phase: GIA; Post GIA Status: Under Construction
- Queue status
- Withdrawn
- Entered queue
- 14 November 2016
- Agreement signed
- 8 March 2019
- Proposed online date
- April 2021
- Withdrawn
- October 2025
Location
Marker shows the centre of Breckinridge County; the queue data does not give exact sites.
Other requests in Breckinridge County
- Solar project J3165, Breckinridge CountySolar Β· 100 MW Β· in study
- Solar + storage project LGE-GIS-2024-005, Breckinridge CountySolar + storage Β· 200 MW Β· withdrawn
- Solar project J3245, Breckinridge CountySolar Β· 150 MW Β· withdrawn
- Solar project LGE-GIS-2019-004, Breckinridge CountySolar Β· 100 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem