United States › Grid › Interconnection queues › Maryland
OTHER · PJMDickerson CT1 (D-CT1)
Dickerson CT1 (D-CT1) is a 5.0 MW other request built and operating in the PJM interconnection queue, in Montgomery County, Maryland, connecting to PEPCO.
Request details
- Queue ID
- W3-105
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- PEPCO
- Connection point (POI)
- Dickerson 230kV
- Location
- Montgomery County, Maryland
- Technology
- Oil: 5.0 MW
- Total requested
- 5.0 MW
- Service type
- Network resource (NRIS)
- Study phase
- Available studies: Feasibility Study, System Impact Study; Interim/Interconnection Service Agreement: Document Posted
- Queue status
- Operational
- Entered queue
- 29 October 2010
- Proposed online date
- December 2011
- Came online
- August 2011
Location
Marker shows the centre of Montgomery County; the queue data does not give exact sites.
Other requests in Montgomery County
- Fourth QuarterBattery storage · 500 MW · agreement signed
- Gas project W4-010, Montgomery CountyGas · 29.1 MW · built
- NIH Unit 1Other · 25.0 MW · built
- GSA Federal Research Center (FDA)Gas · 19.5 MW · built
- DickersonGas · 16.0 MW · built
- GSA Federal Research Center (FDA)Gas · 8.0 MW · built
- Dickerson HCT1, HCT2, DCT1Gas · 5.0 MW · built
- White OakGas · 4.5 MW · built
- Oaks LFOther · 4.0 MW · built
- Gas project D29, Montgomery CountyGas · 3.0 MW · built
- Gas project I10, Montgomery CountyGas · 2.0 MW · built
- Gude LFOther · 1.0 MW · built
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem