Niagara Windpower

Niagara Windpower is a 70.0 MW onshore wind request withdrawn in the NYISO interconnection queue, in Niagara County, New York, connecting to NYSEG.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Dec 2004 (completed)
  2. Withdrawn / abandonedAug 2019 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
162
Grid region
NYISO (New York)
Utility / transmission owner
NYSEG
Developer
AES Somerset, LLC
Connection point (POI)
Somerset Switch Yard
Location
Niagara County, New York
Technology
Wind: 70.0 MW
Total requested
70.0 MW
Queue status
Withdrawn
Entered queue
15 December 2004
Withdrawn
August 2019

Location

Marker shows the centre of Niagara County; the queue data does not give exact sites.