ONSHORE WIND Β· WEST

Onshore wind project 95, Tooele County

Onshore wind project 95, Tooele County is a 71.4 MW onshore wind request withdrawn in the West interconnection queue, in Tooele County, Utah, connecting to PacifiCorp.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Oct 2006 (completed)
  2. Withdrawn / abandonedApr 2011 (project stopped here)
  3. ConsentedFeb 2008 (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
95
Grid region
West (non-ISO utilities)
Utility / transmission owner
PacifiCorp
Developer
Pioneer Ridge, LLC
Connection point (POI)
Tooele-Dugway line
Location
Tooele County, Utah
Technology
Wind: 71.4 MW
Total requested
71.4 MW
Service type
Network resource (NRIS)
Study phase
IA signed 2/8/08, Suspended 2/25/08, Withdrawn 4/4/11-End of Suspension
Queue status
Withdrawn
Entered queue
6 October 2006
Agreement signed
8 February 2008
Proposed online date
December 2007
Withdrawn
April 2011

Location

Marker shows the centre of Tooele County; the queue data does not give exact sites.

Power plants in Utah Β· Transmission lines in Utah

Other requests in Tooele County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem