Battery storage project 25-IC-AC, Jackson County

Battery storage project 25-IC-AC, Jackson County is a 288 MW battery storage request withdrawn in the Southeast interconnection queue, in Jackson County, Georgia, connecting to Southern Company.

Queue statusWithdrawn / abandoned
  1. Planning (completed)
  2. Withdrawn / abandonedApr 2025 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
25-IC-AC
Grid region
Southeast (non-ISO utilities)
Utility / transmission owner
Southern Company
Connection point (POI)
Braselton Substation 230 kV (GTC)
Location
Jackson County, Georgia
Technology
Battery: 288 MW
Total requested
288 MW
Service type
Network resource (NRIS)
Study phase
Withdrawn
Queue status
Withdrawn
Withdrawn
April 2025

Location

Marker shows the centre of Jackson County; the queue data does not give exact sites.

Power plants in Georgia Β· Transmission lines in Georgia

Other requests in Jackson County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem