United States β€Ί Grid β€Ί Interconnection queues β€Ί Michigan

SOLAR Β· MISO

Solar project J1546, Monroe County

Solar project J1546, Monroe County is a 150 MW solar request withdrawn in the MISO interconnection queue, in Monroe County, Michigan, connecting to ITC.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Jun 2020 (completed)
  2. Withdrawn / abandonedNov 2020 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
J1546
Grid region
MISO (Midcontinent)
Utility / transmission owner
ITC
Connection point (POI)
Milan - Monroe 345 kV
Location
Monroe County, Michigan
Technology
Solar: 150 MW
Total requested
150 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: GIA Complete; Post GIA Status: Not Started
Queue status
Withdrawn
Entered queue
22 June 2020
Proposed online date
October 2023
Withdrawn
November 2020

Location

Marker shows the centre of Monroe County; the queue data does not give exact sites.

Power plants in Michigan Β· Transmission lines in Michigan

Other requests in Monroe County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem