Southold BESS

Southold BESS is a 20.0 MW battery storage request withdrawn in the NYISO interconnection queue, in Suffolk County, New York, connecting to LIPA.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Oct 2019 (completed)
  2. Withdrawn / abandonedApr 2022 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
911
Grid region
NYISO (New York)
Utility / transmission owner
LIPA
Developer
Dimension NY 1 LLC
Connection point (POI)
Peconic - Southold 69kV
Location
Suffolk County, New York
Technology
Battery: 20.0 MW
Total requested
20.0 MW
Queue status
Withdrawn
Entered queue
1 October 2019
Withdrawn
April 2022

Location

Marker shows the centre of Suffolk County; the queue data does not give exact sites.