United States β€Ί Grid β€Ί Interconnection queues β€Ί Michigan

ONSHORE WIND Β· MISO

Onshore wind project G958, Kent County

Onshore wind project G958, Kent County is a 120 MW onshore wind request withdrawn in the MISO interconnection queue, in Kent County, Michigan.

Queue statusWithdrawn / abandoned
  1. PlanningQueued May 2009 (completed)
  2. Withdrawn / abandonedAug 2010 (project stopped here)
  3. ConsentedAug 2010 (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
G958
Grid region
MISO (Midcontinent)
Connection point (POI)
Kenowa 345kV Substation
Location
Kent County, Michigan
Technology
Wind: 120 MW
Total requested
120 MW
Study phase
Feasibility
Queue status
Withdrawn
Entered queue
15 May 2009
Agreement signed
4 August 2010
Proposed online date
December 2010
Withdrawn
August 2010

Location

Marker shows the centre of Kent County; the queue data does not give exact sites.

Power plants in Michigan Β· Transmission lines in Michigan

Other requests in Kent County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem