Battery storage project J1980, Kent County

Battery storage project J1980, Kent County is a 50.0 MW battery storage request withdrawn in the MISO interconnection queue, in Kent County, Michigan, connecting to METC.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Aug 2021 (completed)
  2. Withdrawn / abandonedOct 2025 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
J1980
Grid region
MISO (Midcontinent)
Utility / transmission owner
METC
Connection point (POI)
Vergennes 138kV
Location
Kent County, Michigan
Technology
Battery: 50.0 MW
Total requested
50.0 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: DPP 3; Post GIA Status: Not Started
Queue status
Withdrawn
Entered queue
23 August 2021
Proposed online date
October 2024
Withdrawn
October 2025

Location

Marker shows the centre of Kent County; the queue data does not give exact sites.

Power plants in Michigan Β· Transmission lines in Michigan

Other requests in Kent County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem